The Newburyport Wastewater Treatment Facility (WWTF) was originally constructed in 1963 as a primary plant and was subsequently upgraded to provide secondary treatment in 1984. In 2001, odor control facilities were added to the plant. The facility provides biological treatment of wastewater prior to discharge of effluent into the Merrimack River. The facility is designed to treat an average daily flow of 3.40 million gallons per day (mgd),
and peak flow of 9.45 mgd.
The WWTF is located at #157 Water Street within the city’s waterfront marine dependent zone.
The objective of the Newburyport WWTF Improvements Project is to
upgrade the facility to provide continuous treatment of all
wastewater flows and pollutant loadings in compliance with its
National Pollutant Discharge Elimination System (NPDES) permit for
the next 20 years. As part of this effort improvements to support facilities (buildings, electrical, instrumentation & control systems, etc.) are also necessary.
A portion of the WWTF Improvements project design has been undertaken with a fast track schedule to take advantage of construction phase state and federal funding sources including the Massachusetts State Revolving Fund (SRF) loan program, the American Recovery and Reinvestment Act (ARRA) funding program and the Green Infrastructure Reserve fund. To maximize the funding contribution for this project and allow for less disruption of the operations process, the work was divided into two construction phases.
The main components of the proposed project include improvement/upgrade of the existing treatment processes and equipment, reconstruction of the existing process building and upgrade of the current aeration system from mechanical surface aeration to fine bubble diffused aeration (which includes the construction of a new building to house
the aeration blower equipment).
The proposed project also includes construction of a new Operations, Control and Laboratory (OCL) building on
the 115 Water Street site adjacent to the WWTF. Until
recently, the site was privately owned and was used for boat sales and storage during the winter.
In October 2009, the city acquired the site through an eminent domain taking. As
previously mentioned, one of the primary reasons for obtaining this
parcel was to provide the contractor with a staging area.
The 115 Water Street site is known to contain petroleum contaminated soils within a portion of the area where the new OCL building is proposed. Some soil remediation measures for this contamination were undertaken by the
previous property owner, though more extensive remediation/removal measures, in areas of proposed construction, are anticipated
as part of the WWTF Improvements project. See Areas of Proposed Work figure for the approximate extents of the proposed work.
The new OCL building has been designed to fit architecturally into the surrounding neighborhood and to incorporate
Leadership in Energy and Environmental Design (LEED) principles, and will be LEED certified following construction. The orientation of this new building has been designed to minimize impacts on neighbor’s views to the Merrimack River, while still providing the necessary connection to the adjacent existing WWTF site. See attached
Conceptual Rendering for a perspective on the entrance to the new OCL building. These architectural and orientation design principles have also been incorporated into the re-construction of the
Process/Operations building and the new Aeration Blower building on the
existing WWTF site.
Bids for Contract No. 1 were opened in December 2009 and include the construction of the OCL Building, many of the process improvements (with the exception of work in the existing headworks, influent pumping, solids dewatering and odor control system) and the aeration system upgrade. Contract No. 2 will include the remainder of the process improvement work and the re-construction of the Process/Operations
building.
Meetings/Hearings for this project have been conducted with the City Council, the Planning Board, the Building Commissioner, the Conservation Commission, the Zoning Board of Appeals, the Fire Chief, the Police
Marshall and other appropriate local officials. A Notice of Intent was filed with the Conservation Commission and an Order of Conditions has been issued. The project has received approvals on the Major Site Plan Review application filed with the Planning Board and on the Special Permit and zoning variances requested from the Zoning Board of Appeals. We have also appeared before the Newburyport Historic Commission regarding building demolition and have coordinated with the Massachusetts Historical Commission, the Department of Environmental Protection Waterways and the local Chapter 91 Citizen’s Committee. Additionally, two public meetings have been held during the design phase of this project (two public meetings were also held during the planning phase).
Public meeting(s) will continue during the construction phases of this project. Please check this site for scheduled dates and locations.
A Traffic Management Plan for this project is included in the construction documents. This plan requires that construction vehicles for this project travel on the following roads to and from the project site:
- Interstate 95
- Scotland Road/Graf Road
- Low Street (east of Graf Road)
- Pond Street
- High Street (east of Pond Street)
- Federal Street
- Water Street
Several provisions of this project specifically address goals to maintain and enhance public use and access to tidelands and waterways. These provisions include the following:
- A new 8-foot wide concrete sidewalk will connect the sidewalk on Water Street (and crosswalk to Lime Street) with the existing walking path that is adjacent to the Merrimack River. This will preserve and improve pedestrian access to the riverfront. See
Site Plan and Sections of Sidewalk figure.
- The design includes improved access to the American Yacht Club. A new
24-foot access drive to allow public access to OCL building as well as member
access. This will allow for easier access for boats in tow, and at the same
time, protects the existing use of this waterfront property.
- Improved site lighting and buried utilities.
- The proposed Operations Control and Laboratory (OCL) building includes a
conference room for staffing meetings and public meetings such as the Sewer Commission's regularly scheduled monthly meeting.
- A stormwater management design has been completed for use during and after construction to protect water quality.
- Minimized construction impact based on the use of a construction staging area
located on the 115 Water Street site.
A project meeting was held on June 22, 2010 to discuss project construction
items. Please see linked Public Meeting Summary for specific information
discussed.
|